Skip to content

Parking Garage​

St. Elizabeths East - Parking Garage at Parcel 6

The Phase 2 Parking Garage is a design-build project that includes designing and constructing a parking garage with 750 parking spaces within a multi-level parking structure. This project is currently in the design phase.

Design started in Spring 2020.

Construction begins in Fall 2020 and ends in early 2022.

Informational Construction Links

ParkingGarage (1)

PARKING GARAGE UPDATES

August 2023

CFA Screening, vine plants and newly stained columns at the sound entrance of the Garage
Parking Garage and Temporary 13th St
CFA Screening and newly stained beams at the exit on the west end of the Garage
CFA Screening and the vines on the south end of the Garage

July 2023

CFA Screening, vine plants and newly stained columns at the sound entrance of the Garage
Parking Garage and Temporary 13th St
CFA Screening and newly stained beams at the exit on the west end of the Garage
CFA Screening and the vines on the south end of the Garage

June 2023

CFA Screening, vine plants and newly stained columns at the sound entrance of the Garage
Parking Garage and Temporary 13th St
CFA Screening and newly stained beams at the exit on the west end of the Garage
CFA Screening and the vines on the south end of the Garage

May 2023

CFA Screening, vine plants and newly stained columns at the sound entrance of the Garage
Parking Garage and Temporary 13th St
CFA Screening and newly stained beams at the exit on the west end of the Garage
CFA Screening and the vines on the south end of the Garage

April 2023

CFA Screening, vine plants and newly stained columns at the sound entrance of the Garage
Parking Garage and Temporary 13th St
CFA Screening and newly stained beams at the exit on the west end of the Garage
CFA Screening and the vines on the south end of the Garage

March 2023

CFA Screening, vine plants and newly stained columns at the sound entrance of the Garage
Parking Garage and Temporary 13th St
CFA Screening and newly stained beams at the exit on the west end of the Garage
CFA Screening and the vines on the south end of the Garage

February 2023

CFA Screening, vine plants and newly stained columns at the sound entrance of the Garage
Parking Garage and Temporary 13th St
CFA Screening, vine plants and newly stained columns on the south end of the Garage
CFA Screening and the vines on the south end of the Garage

January 2023

CFA Screening, vine plants and newly stained columns at the sound entrance of the Garage
Parking Garage and Temporary 13th St
CFA Screening and newly stained beams at the exit on the west end of the Garage
CFA Screening and the vines on the south end of the Garage

December 2022

CFA Screening, vine plants and newly stained columns at the sound entrance of the Garage
Parking Garage and Temporary 13th St
CFA Screening and newly stained beams at the exit on the west end of the Garage
CFA Screening and the vines on the south end of the Garage

November 2022

CFA Screening, vine plants and newly stained columns at the sound entrance of the Garage
Parking Garage and Temporary 13th St
CFA Screening and newly stained beams at the exit on the west end of the Garage
CFA Screening and the vines on the south end of the Garage

October 2022

CFA Screening, vine plants and newly stained columns at the sound entrance of the Garage
Parking Garage and Temporary 13th St
CFA Screening and newly stained beams at the exit on the west end of the Garage
CFA Screening and the vines on the south end of the Garage

July 2022

Final Punchlist Walk
Parking Garage and Temporary 13th St
CFA Screening and newly stained beams at the exit on the west end of the Garage
CFA Screening and the vines on the south end of the Garage

June 2022

Parking Garage and Temporary 13th St
Traffic Coating on Top Level of Garage
CFA Screening installation on the south-west end of the Garage
Front of Building Prior to Screen Installation

May 2022

Parking Garage and Temporary 13th St
Traffic Coating on Top Level of Garage
Servers and Temporary Switch Installed in IT Room
Front of Building Prior to Screen Installation

April 2022

Parking Garage and Temporary 13th St
Permanent Lighting Installed
Bead Blasting in Preparation for Traffic Coating
GSG Trailers Demobilized from Site

March 2022

Parking Garage and Temporary 13th St
Landscaping Installation
Final Condition of Wetlands
Permanent Generator Onsite

December 2021

Light Fixtures and Bollards with Parking Level Stencil
Parking Garage from Temporary 13th St
Granite Curb Installation
Temporary 13th St Base Asphalt and Landscaping

November 2021

Precast End of November
Topping Slabs Being Poured on Parking Deck
Plantings on East Side of Building
Temporary 13th St Subgrade and Landscaping

October 2021

Precast End of October
Beginning Lightweight Structural Fill
Lightweight Structural Fill at End of October
Switchgear Installed

SEE WHAT'S NEW