St. Elizabeths East - 13th Street Roadway and Utilities
Phase 4 13th Street Roadway and Utilities is a design-bid-build (DBB) project to construct a new roadway for 13th Street and Cherry Street that includes utilities and relocation of the substation.
Construction started March 15, 2022.
Construction completion tentative date is December 19, 2023.
ROADAY & UTILITIES UPDATES
August 2023
Base Asphalt on Cherry St
Installation of 12” Waterline on 13th St
Installation of 4 Way Conduit Along 13th St
July 2023
Stairs at the ESA Building with Temporary Handrails
Base Course on Cherry next tor ESA
Installation of MH 205
June 2023
Installing Sanitary Sewer MH 15C and 9
Base Paving from Cypress to Pecan
Continue Installation of Cobblestone Pavers
May 2023
Installing Hospital Storm MH 4B and MH4
Hauling Dirt off the Stockpile by 13th and Cypress
Continue Installation of Storm Strucrues in the Ravine
April 2023
Grading between Pecan Street and Cypress Street.
Hauling Dirt off the Stockpile by 13th and Cypress
Subgrade for Maintenance Road behind Parking Garage
March 2023
Demolition of Cypress Street
Base Asphalt – 13th Street
North View of 13th Street
February 2023
Installing Sanitary Sewer MH 15C and 9
Hauling Dirt off the Stockpile by 13th and Cypress
LIDs Along the East Side of 13th
January 2023
Installing Sanitary Sewer MH 15C and 9
Hauling Dirt off the Stockpile by 13th and Cypress
LIDs Along the West Side of 13th
December 2022
Installing Sanitary Sewer MH 15C and 9
Hauling Dirt off the Stockpile by 13th and Cypress
LIDs Along the West Side of 13th
November 2022
Installing Sanitary Sewer MH 15C and 9
Hauling Dirt off the Stockpile by 13th and Cypress
LIDs Along the West Side of 13th
October 2022
Installing Sanitary Sewer MH 15C and 9
Hauling Dirt off the Stockpile by 13th and Cypress
LIDs Along the West Side of 13th
July 2022
Installation of Storm Sewer Pipe at MH10 OFF
Stairs at the ESA Building with Temporary Handrails